The US Navy has changed its mind about what the next batch of Growler jamming pods should be. On Friday 13 November 2026, the Pentagon’s daily contract announcement listed a $42,121,481 modification for Raytheon that converts low-rate initial production Lot Five of the Next Generation Jammer Mid-Band (NGJ-MB) to the newer “mid-band extended” configuration.
The number of pods does not change. What changes is what is inside them. Lot Five was ordered in May 2025 as standard Mid-Band shipsets; under the new modification, the same lot will be built to the extended standard instead, the version designed to reach further and cover more of the threat spectrum.
Informazioni rapide
- Annunciato: Friday 13 November 2026, US Department of War contracts
- Contractor: Raytheon Co., El Segundo, California
- Valore: $42,121,481 modification (P00010) to contract N0001925C0104
- Che cosa: Converts Lot Five of NGJ-MB low-rate initial production to the mid-band extended configuration
- Quantity: Unchanged; no increase to Lot Five
- Main work sites: McKinney, Texas (65.7%) and Forest, Mississippi (20.4%)
- Completamento: Expected May 2029
- Aeromobili: EA-18G Growler
What the contract says
The announcement is precise. The modification, P00010 to contract N0001925C0104, is a mix of fixed-price-incentive and cost-plus-fixed-fee work and covers manufacture, integration, test, delivery, spares, non-recurring engineering, logistics support and technical data. In the contract’s own words, it “converts the existing production requirement to the mid-band extended configuration without increasing the existing Lot Five quantity.”
Most of the work, 65.7 per cent, will be done in McKinney, Texas, with 20.4 per cent in Forest, Mississippi, 13.4 per cent in El Segundo, California, and 0.5 per cent in Andover, Massachusetts. It is due to be finished in May 2029. The contract was not competed, and Naval Air Systems Command at Patuxent River, Maryland, is the contracting activity.

The money comes from three pots: about $5.25 million of fiscal 2027 Navy aircraft procurement funds, $28.8 million of fiscal 2025 aircraft procurement funds and $8.05 million from the Navy’s foreign cooperative projects line, all obligated at the time of award. The Next Generation Jammer is a cooperative programme with the Aeronautica militare reale australiana, which flies the Growler too.
From Mid-Band to Mid-Band Extended
The Next Generation Jammer is the replacement for the AN/ALQ-99, the jamming pod the Navy has flown since 1972 on aircraft from the EA-6B Prowler to today’s EA-18G Growler. The programme was split into three pods by frequency: Low-Band, Mid-Band and High-Band. Raytheon builds the Mid-Band pod, designated AN/ALQ-249, which reportedly covers roughly 2 to 6 GHz.
The extended version, NGJ-MBX, grew out of a gap. According to DefenseScoop, the Navy started a change to the Mid-Band programme in 2023 to develop a pod with increased range that would also cover specific gaps in the upper frequencies, as the quickest answer to near-term threats while the High-Band pod remained unfunded. Raytheon received a $192 million engineering and manufacturing development contract for MBX in September 2024.
At the time, a Raytheon spokesperson told DefenseScoop that the upgraded MBX arrays would be built into new production pods and also retrofitted to Mid-Band systems already in service. Moving Lot Five onto the extended standard now means those pods should leave the factory with the upgrade, rather than needing it later.
Naval News looks at RTX’s Next Generation Jammer at the Sea Air Space 2026 exhibition.
Where it fits in the Growler’s jamming suite
The Mid-Band pod is not the Growler’s only new jammer. L3Harris is building the Low-Band pod, and Afterburner covered its $876 million follow-on award in September. Until a High-Band pod exists, the new pods fly alongside legacy ALQ-99 equipment, which is why stretching the Mid-Band upwards matters.
Production of the Mid-Band pod has been running for some time. Raytheon won a $590 million follow-on production contract in December 2024 and about $580 million for Lot Five shipsets in May 2025. The modification announced on 13 November does not add to that order; it upgrades what the Navy has already bought.
For the Growler crews, the practical result is simple. The next pods to arrive will be the extended version from the start, with more reach and wider frequency coverage than the Mid-Band pods now on the squadrons’ jets.