On Thursday in Moscow, Aeroflot signed for 90 more Yakovlev MC-21-310s. That takes the national carrier’s commitment to 108 aircraft, with deliveries running from 2029 to 2032, plus simulators, crew training and 22 years of support.
The number of MC-21s currently carrying fare-paying passengers anywhere in the world is zero.
That gap between the order book and the apron is the entire story of Russian civil aviation right now.
Informazioni rapide
- What was signed: a contract for 90 Yakovlev MC-21-310s, in Moscow on 18 September 2026
- Who signed: Aeroflot with three Rostec companies — United Aircraft Corporation, the leasing arm Aviacapital-Service, and engine maker UEC
- Total commitment: 108 aircraft, including 18 from a 2023 contract due in 2027 and 2028
- Delivery schedule for the new 90: 14 in 2029, 18 in 2030, 24 in 2031 and 34 in 2032
- Motori: Russian Aviadvigatel PD-14 turbofans
- Capacità: up to 211 passengers
- Also included: simulators, crew training, and 22 years of technical support for all 108 aircraft
- In airline service today: nessuno
What Was Actually Signed
The contract went through Aeroflot and three companies inside the Rostec state conglomerate: United Aircraft Corporation, which builds the aircraft, the leasing arm Aviacapital-Service, which finances it, and United Engine Corporation, which supplies the powerplants. Everything in the deal is state-owned on both sides. This is an internal transfer dressed as a commercial order.
The aircraft seats up to 211 passengers and is powered by Aviadvigatel PD-14 turbofans. The delivery profile is steep: 14 aircraft in 2029, then 18, then 24, then 34 in 2032.

The Aeroplane Changed Under Sanctions
The MC-21 that Putin walked around at the Irkutsk Aviation Plant in July 2026 is not the aircraft that was designed. Sanctions imposed after the invasion of Ukraine forced United Aircraft Corporation to replace the Western engines, the composite wing and a long list of other components with Russian alternatives.
Every substitution cost weight. The post-sanctions aircraft is reported to be about six tonnes heavier than the original, which means it can no longer fly Moscow to Vladivostok nonstop as it was supposed to. In an exchange caught on camera during the Irkutsk visit, Putin told Rostec chief Sergei Chemezov the aircraft needed to fly farther. Chemezov replied that they would work on it, and that a longer-range version was under development.
The cost went the same direction. In June 2026 the Russian government raised the projected price of the first 18 localised aircraft from 58.3 billion roubles to 96.1 billion, an increase of nearly two-thirds. Per aircraft, that is roughly 5.34 billion roubles, against 3.14 to 3.29 billion estimated in 2023.
A critical look at how the MC-21 programme got here, one of the most-watched treatments of the subject.
The People Who Built It Are Sceptical
Kirill Zhirikhin worked on testing the MC-21’s capabilities at Russia’s Central Aerohydrodynamic Institute, TsAGI, from 2007 to 2022. He is not a Western analyst guessing from outside.
His objection is not about the aeroplane. He credits UAC with real progress on the design. It is about the industrial base behind it, and about people.
Zhirikhin’s assessment is that the MC-21 remains at least fifteen years behind its foreign competitors, and that production will be limited: enough aircraft to demonstrate the programme exists and to move through state-controlled channels, not enough to become a mass-produced airliner.
The Fleet It Is Supposed to Replace
More than 400 foreign-owned aircraft, mostly Boeings and Airbuses, stayed in Russia after Western leasing companies were forced to terminate their contracts. Those aircraft still carry the overwhelming majority of Russian passengers, kept flying through cannibalisation, improvised parts channels and domestic maintenance capability that Aeroflot has been authorised to build for Airbus and Boeing engines.
Against that, 108 MC-21s delivered on time by 2032 would be a partial replacement at best. And the same plant in Irkutsk that builds the MC-21 also builds Su-30 fighters, in a country whose industrial capacity and skilled labour have been pulled hard toward defence.
Four aircraft are supposed to be finished by the end of this year and handed to Aeroflot once certification is complete. That is the number that matters, and it is the number to watch in January.
Sources: FlightGlobal; aeroTELEGRAPH; TASS; The Moscow Times and VPost; Air Data News.