India Built 30 New Fighters It Cannot Fly

by | Jun 22, 2026 | Military Aviation, News | 0 comments

On the flight line at Hindustan Aeronautics in Nashik and Bengaluru sit some of the most modern fighter jets India has ever built: brand-new Tejas Mk1A light fighters in Indian Air Force grey, radars fitted, flight-test boxes ticked. There is just one problem. Not a single one has been formally handed to the Air Force.

By mid-2026 HAL had assembled, flown and tested roughly thirty Mk1A airframes. The jets are, by the company’s own account, essentially finished. What they are missing is the one component HAL cannot build itself — the engine.

It is one of the strangest bottlenecks in modern military aviation: a fleet of combat aircraft, complete in almost every respect, grounded for want of a turbofan that has to cross an ocean to reach them.

Quick FactsAircraft: HAL Tejas Mk1A — single-engine 4.5-generation light fighter
Built & flight-tested: around 30
Formally delivered to the IAF: zero
Engine: General Electric F404-IN20 (about 84 kN with afterburner)
On order: 83 (2021) plus 97 more cleared in 2025
The bottleneck: late F404 engine deliveries from GE — and, in HAL’s words, “no Plan B”

Thirty Jets, Nowhere to Go

The Mk1A is the upgraded version of India’s home-grown Tejas — better radar, electronic warfare suite, beyond-visual-range missiles and a faster turnaround between sorties. The Air Force ordered 83 of them in 2021 in a deal worth around ₹48,000 crore, and in 2025 the government cleared a follow-on batch of 97 more, taking the total on order to roughly 180 aircraft.

The airframes have not been the problem. HAL says five jets are fully built to the contracted standard and ready to hand over, with around thirty manufactured and tested in total. The aircraft fly. They simply cannot be delivered, because delivery means a complete, engine-fitted jet — and the engines keep arriving late.

HAL Tejas Mk1A taking off at Aero India 2025
A Tejas Mk1A rotates at Aero India 2025. The airframes are flying and tested — they are waiting on engines, not on aerodynamics. Photo: Wikimedia Commons

An Engine Problem, Not an Airframe Problem

The Tejas Mk1A is a single-engine fighter, and that engine is the General Electric F404-IN20, producing roughly 84 kilonewtons of thrust in afterburner. India does not yet build it. Every Mk1A engine is manufactured by GE in the United States and shipped to HAL for integration — which means the entire Indian programme moves at the speed of one American production line.

That line has not kept pace. GE’s F404 deliveries, contracted years ago, slipped repeatedly; a batch expected by the end of March 2026 came and went without the engines arriving. HAL has so far received only the first handful, which are being mated to waiting airframes. Frustrated by the delays, HAL confirmed it had imposed liquidated damages — financial penalties — on GE for missing its timelines.

General Electric F404 turbofan engine
The General Electric F404 — the single turbofan the entire Mk1A line depends on. HAL has described its engine situation bluntly: there is “no Plan B.” Photo: Wikimedia Commons

HAL’s chairman has tried to project confidence that the worst is over, pointing to GE’s new tooling and a promised ramp-up: 24 engines in financial year 2026-27, climbing to about 30 a year after that.

“Since the airframes are ready and tested, it’s just about the integration of engines. We are looking at the delivery of 12 aircraft by the end of this financial year.”
Dr D.K. Sunil — Chairman and Managing Director, Hindustan Aeronautics Limited

Why a Late Engine Is a Strategic Problem

The delay lands at an awkward moment. The Indian Air Force has been sliding well below its sanctioned strength of 42 fighter squadrons — it now fields around 30 — even as it retires the last of its Soviet-era MiG-21s. The Mk1A was meant to be the jet that filled that gap. Every month the engines are late is a month the squadron numbers stay thin, with both China and Pakistan on India’s mind.

To break the dependence, India is doubling down rather than backing away. In late 2025 HAL signed a fresh deal with GE — reported at around one billion dollars — for 113 more F404 engines to be delivered between 2027 and 2032, enough to cover the Mk1A fleet with a buffer. Longer term, the heavier Tejas Mk2 and the stealthy AMCA are meant to move India toward engines it has a real stake in building.

For now, though, the picture is unique in its quiet absurdity: one of the world’s largest air forces has dozens of brand-new fighters it has built, flown and proven — and still cannot fly into service, because the one part it cannot make itself is stuck in a queue half a world away.

Sources: Hindustan Aeronautics Limited statements; Business Standard; Defence.in; Indian Defence Research Wing; Swarajya; FlightGlobal.

Related Posts

The Flying Whales That Built Apollo

The Flying Whales That Built Apollo

On a September morning in 1962, the air traffic controllers at Van Nuys Airport made a phone call. They told the local police and fire departments to stand by. Out on the ramp sat the most absurd aeroplane anyone there had ever seen — a Boeing airliner whose...

Missing 25 Feet of Wing, He Landed It

Missing 25 Feet of Wing, He Landed It

At 11,000 feet over the wooded hills north of New York City, on a grey December afternoon, two airliners that were never supposed to meet found themselves on a converging path. Within seconds the tip of a Boeing 707’s left wing sliced through the triple tail of...