IAR-99 SM: Romania Receives First Two Modernised Jet Trainers

by | Nov 17, 2026 | Aviation militaire, Nouvelles | 0 comments

Six years after the contract was signed and two years after the original deadline, Romania finally has its first modernised jet trainers. On Monday 16 November 2026, a Ministry of National Defence acceptance commission at Craiova took delivery of the first two IAR-99 SM aircraft from Avioane Craiova, the company that designed and built the type.

The pair are the first of ten IAR-99s being upgraded to the new Standard Modernizat configuration. They will train the pilots who go on to fly the F-16, which is now the backbone of the Romanian Air Force.

Informations clés

  • Aéronef: IAR-99 SM (Standard Modernizat) advanced jet trainer
  • Accepted: Monday 16 November 2026, Craiova
  • Delivered so far: 2 of 10 on contract
  • Contractor: Avioane Craiova, with avionics from Elbit Systems
  • Contracter: Signed 14 August 2020, 275 million lei excluding VAT
  • Original deadline: All ten in 2024
  • Suivant: Third aircraft due by end of November 2026 (weather permitting); remaining seven by 31 December 2027, according to Adevărul
  • Rôle: Lead-in training for the F-16; close air support

What was delivered

According to the ministry statement reported by Mediafax and DefenseRomania, the final acceptance commission was made up of specialists from the General Directorate for Armaments and the Air Force Staff. The two aircraft are part of the programme “Revitalisation and modernisation of the IAR-99 aircraft”, which aims to give Romania an advanced jet-training capability for the move to the F-16 and to keep a close air support capability.

The ministry describes the IAR-99 SM as the step in which student pilots move from propeller-driven turboprops to jets. Agerpres adds that the programme also aims to keep a capability against slow-flying aerial targets, a role that has gained weight as drones keep straying into Romanian airspace from the war next door.

IAR 99 jet trainer with a yellow access ladder inside the Avioane Craiova factory hangar with workers in blue overalls
An IAR 99 inside the Avioane Craiova factory on 14 August 2020, the day the IAR-99 SM modernisation contract was signed. Photo: Romanian Government (gov.ro) / Wikimedia Commons, attribution licence

The contract for the ten aircraft was signed between the ministry and Avioane Craiova on 14 August 2020 and is worth 275 million lei before VAT. It originally ran for four years, and DefenseRomania notes that all ten aircraft were supposed to be delivered in 2024. For the new avionics, Avioane Craiova brought in Israel’s Elbit Systems, which announced its part of the work in December 2020.

A programme that nearly stalled

The delays were long and expensive. Agerpres reports that the company cited problems obtaining equipment and components, blamed on the COVID-19 pandemic, the war in Ukraine and the security situation in the Middle East. According to the Romanian Court of Accounts findings quoted by the agency, Avioane Craiova had received advances of more than 98 million lei, the ministry calculated late-delivery penalties of about 3.62 million lei, and in February 2026 part of the bank guarantee on the advance, about 41.94 million lei, was called in.

To get the first jets out of the door, the ministry accepted a partial delivery. DefenseRomania reports that the two aircraft were received without a Honeywell GPS anti-spoofing system, which is to be delivered later. Radu Miruță, a former defence minister, had told the outlet that the state had made major concessions to rescue both the project and the company.

“Vă repet, s-au făcut toate concesiile din două rațiuni. Unu: avem nevoie de acest avion la armată. Doi: e critic să salvăm și Avioane Craiova.”
Radu Miruță — Former Romanian defence minister, to DefenseRomania (Romanian original)

Victor Peța, the union leader at Avioane Craiova, told Agerpres that the acceptance commission worked through Friday, Saturday and Sunday to finish the job, and that a third aircraft should follow by the end of November if the weather allows the necessary test flights. Adevărul reports that the remaining seven are due by 31 December 2027.

“Astăzi am predat două avioane și urmează ca până la sfârșitul lunii să mai predăm încă unul. Valoarea contractului este de 275 de milioane de lei. Programul continuă.”
Victor Peța — Union leader at Avioane Craiova, to Agerpres, 16 November 2026 (Romanian original)

Romania’s home-grown Hawk

Le IAR 99 Șoim, Romanian for hawk, is the first jet trainer both designed and built in Romania. Work began in 1975, the prototype first flew on 21 December 1985 and series production started in 1987. The single-engine, tandem two-seater gradually replaced the Aero L-29 Delfín et L-39 Albatros as the Romanian Air Force’s main jet trainer.

Two Romanian Air Force IAR-99 jet trainers flying overhead in close formation against a blue sky
Two Romanian Air Force IAR-99s overhead at an air show at Câmpia Turzii in July 2017. The type has been the service’s main jet trainer since replacing the L-29 and L-39. Photo: Staff Sgt. Jonathan Snyder, US Air Force / Wikimedia Commons, public domain

In the late 1990s Elbit upgraded the type as a lead-in trainer for the MiG-21 LanceR, producing the IAR 99 C Șoim. Twelve of those were delivered between 2003 and 2008, while eleven aircraft stayed in the older Standard configuration. It is the remaining ten Standard airframes that are now being brought up to IAR-99 SM level.

TVR Craiova reports on Avioane Craiova’s work modernising the first IAR-99 SM (Romanian).

With the MiG-21 retired and Romania building its fighter force around F-16s, the IAR-99 SM has a clear job: bridge the gap between the turboprop school and the Viper cockpit. Two are now in the ministry’s hands. The question for Craiova is whether the other eight can follow faster than the first two did.

Sources: Romanian Ministry of National Defence (via Mediafax and DefenseRomania), Agerpres, Adevarul, DefenseRomania, Mediafax, Wikipedia (IAR 99)

Header photo: Coffeecake27 / Wikimedia Commons, CC BY-SA 4.0

Foire aux questions

When did Romania receive the first modernised IAR-99 SM?
Romania’s Ministry of National Defence accepted the first two IAR-99 SM jet trainers at Craiova on Monday 16 November 2026. They are the first of ten IAR-99 aircraft being modernised by Avioane Craiova under a contract signed in August 2020, which originally called for all ten to be delivered in 2024.
How many IAR-99 SM aircraft has Romania ordered?
Romania’s contract with Avioane Craiova covers the modernisation of ten IAR-99 Standard aircraft to IAR-99 SM configuration. Two were accepted on 16 November 2026, a third is expected by the end of November if weather allows, and Adevărul reports the remaining seven are due by 31 December 2027.
Who modernises the IAR-99 for Romania?
The IAR-99 SM modernisation is carried out by Avioane Craiova, the Romanian company that designed and built the IAR 99. The avionics come from Israel’s Elbit Systems, which Avioane Craiova contracted for the work. The contract with the Ministry of National Defence is worth 275 million lei before VAT.
Why was the IAR-99 SM programme delayed?
Avioane Craiova blamed difficulties obtaining equipment and components, linked to the COVID-19 pandemic, the war in Ukraine and the Middle East security situation. The ministry imposed penalties of about 3.62 million lei and in February 2026 called in part of the bank guarantee on the advance payment.
What is the IAR-99 SM used for?
The IAR-99 SM is an advanced jet trainer that moves Romanian student pilots from turboprop aircraft to jets and prepares them for the F-16. The programme also keeps a close air support capability and, according to Agerpres, a capability against slow-flying aerial targets.
Can I fly in an L-39?
Yes. MiGFlug offers flights in the L-39 Albatros, the Czechoslovak jet trainer that the IAR 99 replaced in Romanian service. More than 2,900 L-39s were built and over 30 air forces flew it. See the Vol du L-39 Albatros page for locations and booking.

Articles similaires

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *