Six years after the contract was signed and two years after the original deadline, Romania finally has its first modernised jet trainers. On Monday 16 November 2026, a Ministry of National Defence acceptance commission at Craiova took delivery of the first two IAR-99 SM aircraft from Avioane Craiova, the company that designed and built the type.
The pair are the first of ten IAR-99s being upgraded to the new Standard Modernizat configuration. They will train the pilots who go on to fly the F-16, which is now the backbone of the Romanian Air Force.
Informations clés
- Aéronef: IAR-99 SM (Standard Modernizat) advanced jet trainer
- Accepted: Monday 16 November 2026, Craiova
- Delivered so far: 2 of 10 on contract
- Contractor: Avioane Craiova, with avionics from Elbit Systems
- Contracter: Signed 14 August 2020, 275 million lei excluding VAT
- Original deadline: All ten in 2024
- Suivant: Third aircraft due by end of November 2026 (weather permitting); remaining seven by 31 December 2027, according to Adevărul
- Rôle: Lead-in training for the F-16; close air support
What was delivered
According to the ministry statement reported by Mediafax and DefenseRomania, the final acceptance commission was made up of specialists from the General Directorate for Armaments and the Air Force Staff. The two aircraft are part of the programme “Revitalisation and modernisation of the IAR-99 aircraft”, which aims to give Romania an advanced jet-training capability for the move to the F-16 and to keep a close air support capability.
The ministry describes the IAR-99 SM as the step in which student pilots move from propeller-driven turboprops to jets. Agerpres adds that the programme also aims to keep a capability against slow-flying aerial targets, a role that has gained weight as drones keep straying into Romanian airspace from the war next door.

The contract for the ten aircraft was signed between the ministry and Avioane Craiova on 14 August 2020 and is worth 275 million lei before VAT. It originally ran for four years, and DefenseRomania notes that all ten aircraft were supposed to be delivered in 2024. For the new avionics, Avioane Craiova brought in Israel’s Elbit Systems, which announced its part of the work in December 2020.
A programme that nearly stalled
The delays were long and expensive. Agerpres reports that the company cited problems obtaining equipment and components, blamed on the COVID-19 pandemic, the war in Ukraine and the security situation in the Middle East. According to the Romanian Court of Accounts findings quoted by the agency, Avioane Craiova had received advances of more than 98 million lei, the ministry calculated late-delivery penalties of about 3.62 million lei, and in February 2026 part of the bank guarantee on the advance, about 41.94 million lei, was called in.
To get the first jets out of the door, the ministry accepted a partial delivery. DefenseRomania reports that the two aircraft were received without a Honeywell GPS anti-spoofing system, which is to be delivered later. Radu Miruță, a former defence minister, had told the outlet that the state had made major concessions to rescue both the project and the company.
Victor Peța, the union leader at Avioane Craiova, told Agerpres that the acceptance commission worked through Friday, Saturday and Sunday to finish the job, and that a third aircraft should follow by the end of November if the weather allows the necessary test flights. Adevărul reports that the remaining seven are due by 31 December 2027.
Romania’s home-grown Hawk
Le IAR 99 Șoim, Romanian for hawk, is the first jet trainer both designed and built in Romania. Work began in 1975, the prototype first flew on 21 December 1985 and series production started in 1987. The single-engine, tandem two-seater gradually replaced the Aero L-29 Delfín et L-39 Albatros as the Romanian Air Force’s main jet trainer.

In the late 1990s Elbit upgraded the type as a lead-in trainer for the MiG-21 LanceR, producing the IAR 99 C Șoim. Twelve of those were delivered between 2003 and 2008, while eleven aircraft stayed in the older Standard configuration. It is the remaining ten Standard airframes that are now being brought up to IAR-99 SM level.
TVR Craiova reports on Avioane Craiova’s work modernising the first IAR-99 SM (Romanian).
With the MiG-21 retired and Romania building its fighter force around F-16s, the IAR-99 SM has a clear job: bridge the gap between the turboprop school and the Viper cockpit. Two are now in the ministry’s hands. The question for Craiova is whether the other eight can follow faster than the first two did.